Highway 44 Improvement Project information.
Contact information
Contractor Information
Justin Lechtenberg Division Manager Reilly Construction Co., Inc. PO Box 99 110 East Main Ossian, IA 52161 (563) 532-9211 (voice) (563) 532-9759 (fax) (515) 460-2252 (cell)
Emergency Phone Numbers
Recent Project Updates
Notes from the Engineer (May 27, 2010) Notes from the Engineer (June 7, 2010) Notes from the Engineer (June 14, 2010) Notes from the Engineer (June 25, 2010) Notes from the Engineer (July 02, 2010) Notes from the Engineer (July 09, 2010) Notes from the Engineer (July 16, 2010) Notes from the Engineer (July 23, 2010) Notes from the Engineer (July 30, 2010) Notes from the Engineer (August 6, 2010) Notes from the Engineer (August 13, 2010) Notes from the Engineer (August 20, 2010) Notes from the Engineer (August 27, 2010)
General Information
Project Timeline Notes From the Engineer Project Overview. (PDF) Project funding (PDF)
Traffic and Detour Plans May 24th - September 1st Phase 1: Construction From West City Limits to Maplewood Drive (PDF) Phase 3: Construction From Maplewood Drive to James Street (PDF)
June 14th - September 1st Phase 4: Construction From South James Street from SE 2nd Street to HWY 44; HWY 44 Southy Lanes from James Street to Ewing Street (PDF) September 1st - October 15th Phase 2: Construction of HWY 44 North Lanes from West City Limits to Maplewood Drive (PDF)
September 1st - October 15th Phase 5: Construction of HWY 44 South Lanes From Ewing Street to NE Circle Drive (PDF)
July 21st - September 1st Phase 7: Widening of North James Street from HWY 44 to NW 3rd Street Place (PDF)
October 15th - December 1st Phase 6: Widening of HWY 44 North Lanes From James Street to NE Circle Drive (PDF)