If you have any questions, please contact John Gade with FOX Engineering at 515-233-0000 or by
email at jmg@foxeng.com.
N James Street Improvement Project
Construction Notice - Thursday September 21st:  The contractor plans to close the N James ST / 18th ST intersection for paving tomorrow, September 22nd at 9 AM. The Daycare and apartment access will be maintained north of the Beaverbrooke / N James ST intersection on a 20' gravel drive adjacent to the recently placed concrete on N James ST.
Please Click Here for Detour and Information  (PDF)

Construction Notice - Wednesday September 20th:
  Crews will be working late into the evening in order to complete a section of pouring. They will be cutting the poured concrete. We apologize for the inconvenience. 

Weekly Update Friday September 15th  (PDF)

What to expect next week: September 18 Monday – September 23 Saturday
• N James St will be paved from Beaverbrooke Blvd north to NE 22nd Circle. Paving will be gapped at intersections, and over the box culvert. The gap at NW 18th St will allow continued traffic access to the Daycare and Chevalia Ridge Apartments. The gaps will be paved later by shorter concrete pours.
• Concrete work will continue for retaining walls next to the box culvert.

Weekly Update Friday September 8th  (PDF)
What to expect next week: September 11 Monday – September 16 Saturday
• Excavation and concrete work will continue for retaining walls next to the box culvert.
• Roadway subbase (crushed stone) will be placed and trimmed to final grade before paving.

Weekly Update Friday September 1st  (PDF)
What to expect next week: September 04 Monday – September 09 Saturday
• NOTE: The morning of Wednesday September 06, the north half of the intersection of North James St and Beaverbrooke Blvd will be closed to traffic. The south half of the intersection will carry head-to-head traffic. This traffic shift will allow subgrade work on the north half of the intersection. Subgrade work is needed before paving the rest of the intersection.
• Subdrain at sides of Phase 1 roadway will be installed north of the culvert.
• Roadway subbase (crushed stone) will be placed and trimmed to final grade before paving.
• Cast-in-place concrete work will continue at the box culvert (culvert walls and top slab).
• Work will begin on retaining walls next to the culvert.

Weekly Update Friday August 25th  (PDF)
What to expect next week: August 28 Monday – September 02 Saturday
• NOTE: The morning of Wednesday August 30, the north half of the intersection of North James St and Beaverbrooke Blvd will be closed to traffic. The south half of the intersection will carry head-to-head traffic. This traffic shift will allow subgrade work on the north half of the intersection. Subgrade work is needed before paving the rest of the intersection.
• Crushed rock subbase will be placed on subgrade.
• Subbase will be trimmed to elevation for paving.
• Cast-in-place concrete work will continue at the box culvert (culvert walls and top slab).

Weekly Update Friday August 18th  (PDF)

What to expect next week: August 21 Monday – August 26 Saturday
• Cast-in-place concrete work will continue at the box culvert.
• Excavation and forming will begin for retaining wall along roadway at the box culvert.
• Subdrain construction will continue.
• Roadway subgrade will be trimmed to elevation to prepare for paving.

Weekly Update Friday August 11th  (PDF)

What to expect next week: August 14 Monday – August 19 Saturday
• Excavation and forming will begin for cast-in-place culvert sections on each end of the tied precast units.
• Phase 2 roadway subgrade will be compacted.

Weekly Update Friday August 4th  (PDF)

What to expect next week: August 07 Monday – August 12 Saturday
• Sand backfill will be placed and compacted around the culvert.
• Soil from a borrow site will be trucked in to build up earth embankment north of the culvert.
• Forming will begin for cast-in-place culvert sections on each end of the tied precast units.
• Phase 2 roadway excavation will continue.
• Storm sewer construction will continue.

Weekly Update Friday July 28th  (PDF)

What to expect next week: July 31 Monday – August 05 Saturday
• Drainage subdrain will be installed alongside the culvert.
• Sand backfill will be placed and compacted around the culvert.
• Roadway embankment will be compacted north and south of the culvert.
• Starting Monday July 31 at 9:00 AM, Phase 2 between Beaverbrooke Blvd and NW 18th St will be closed to traffic. Please see the attached map for the Detour Route. Access to the Daycare and Apartments will be maintained with a gravel road.
• Phase 2 existing pavement will be removed, and storm sewer will be constructed.

Weekly Update Friday July 21st  (PDF)

What to expect next week: July 24 Monday – July 29 Saturday
• A crane will be moved on site to install precast concrete box culvert sections.
• Precast box culvert sections will be delivered and installed.
• Roadway earthwork will continue.

Weekly Update Friday July 14th  (PDF)

What to expect next week: July 17 Monday – July 22 Saturday
• Storm sewer work will continue in Phase 1 and Phase 2.
• A diversion channel will be built to temporarily re-route Little Beaver Creek.
• Excavation will begin for the proposed box culvert.
• A support pad will be built for a crane needed to install precast concrete box culvert sections.

Weekly Update Friday July 7th  (PDF)

What to expect next week: July 10 Monday – July 15 Saturday
• Utility relocation is scheduled to be complete.
• Storm sewer work will continue in Phase 1 south of the Little Beaver Creek bridge.
• Excavation may begin for the proposed box culvert.

Weekly Update Friday June 30th  (PDF)

What to expect next week: July 03 Monday – July 08 Saturday
• The contractor will work Monday July 03, but not Tuesday July 04.
• Storm sewer work will continue in Phase 1.
• Granular shoulders will be added to the Water/Wastewater Treatment Plant road (NE 18th St).
• Topsoil will be spread on roadside of Phase 3 pavement.
• Work will begin on Phase 3 pavement markings.

Weekly Update Friday June 23rd  (PDF)

What to expect next week: June 26 Monday – July 01 Saturday
• Storm sewer work will continue in Phase 1.
• NE 18th St roadbed will be prepared for asphalt paving.
• N James St roadway in Phase 3 will be finish graded outside of pavement, and work will start for pavement markings and signs.

Weekly Update Friday June 16th  (PDF)
What to expect next week: June 19 Monday – June 24 Saturday
• The remaining width of North James St will be paved from NE 14th Ct north to Beaverbrooke Blvd.
• Paving is estimated to begin Tuesday June 20 at 7:00 a.m. The contractor will saw cut pavement joints later into the evening.
• The contractor will continue Phase 1 grading and storm sewer.
• Detours will remain the same. Please see the attached map.

Progress Meeting Minutes June 14th, 2017  (PDF)


Weekly Update Friday June 9th  (PDF)

What to expect next week: June 12 Monday – June 17 Saturday
• Paving of Phase 3 on North James St (NE 14th Ct to Beaverbrooke Blvd ) is planned for Tuesday, June 13.
• Paving will begin on Tuesday at 7:00 a.m., and contractor will be saw cutting the pavement joints until later into the evening.
• Contractor will start Phase 1 pavement removals.
• Detours will remain the same. Please see the attached map.

Weekly Update Friday June 2nd  (PDF)
What to expect next week: June 05 Monday – June 10 Saturday
• Crushed stone will be placed on Phase 3 roadbed as subbase for concrete paving.
• Paving of Phase 3 on North James St (NE 14th Ct to Beaverbrooke Blvd ) is planned for Thursday,
June 08.
• Paving will begin early on Thursday at 6:30 a.m., and contractor will be saw cutting the pavement
joints until later into the evening.
• Detours will remain the same. Please see the attached map.

NOTICE WEDNESDAY MAY 24TH: 
If you were inconvenienced last night due to the construction noise on N James Street near NW 23rd Court the Contractor had an emergency utility stabilization. They were installing a sanitary sewer service and their trench box slid due to the wet soils. There was a gas main in the facility that needed to be protected which required them to work late into the night. They stabilized the trench and protected the gas main.
Thank you for your understanding and patience.

Weekly Update Monday May 15th  (PDF)

What to expect next week: May 15 Monday - May 19 Friday
• Phase 1 work will begin in addition to Phase 3. A detour map is attached.
• North James Street will be closed to thru traffic between NW 18th St and NE 22nd Circle. The detour will begin at 9 a.m. on Tuesday, May 16th.
• Traffic will be detoured to the east using Beaverbrooke Blvd, NE Park Drive, and NE 27th St. • Existing pavement and sidewalks on North James St will be removed.
• Elder Construction will begin work on Phase 1 storm sewers.

IMPORTANT UPDATE FRIDAY MAY 12TH:
The City of Grimes has a change in plans on the N. James Street project that will decrease the overall construction time!
N James Street will be closed to thru traffic between NW Beaverbrooke Blvd & NE 27th Street beginning at 9 am on Tuesday, May 16th. Attached is the revised Detour Plan.
Allowing the contractor to concurrently work in Phase 1 & Phase 3 will save one (1) month on the construction schedule. This plan gives the best opportunity to complete the project in the 2017 construction season versus finalizing the project in the Spring of 2018. This plan will expedite construction, reduce detour time, and open the roadway sooner.
We considered delaying the start of Phase 1 until June 1st (after school is released). We feel that delaying the construction nearly three (3) weeks could push project completion into the Spring of 2018. Thus the roadway would have to be maintained (gravel portions) over the winter and detouring of traffic in the Spring of 2018.
As always, thank you for your patience and understanding as we continue to improve the transportation infrastructure in our City!
Phase 1 and 3 Detour  (PDF)


Weekly Update Monday May 8th  (PDF)

What to expect next week ( May 8th-May 12th): Grading of the roadway will continue. Elder will mobilize equipment, material, and begin construction of storm sewers.

Update Monday May 1st:
  Due to weather, N James Street will remain open to traffic until 9 am on Tuesday May 2nd. The contractor will determine if weather conditions will allow them to work on the project.

North James Street & Bridge Improvements Notice of Construction

What to expect: May 1st - May 5th
  • The Contractor will be stripping topsoil and grading the site to required elevations
  • The pavement removal process will begin
  • Erosion control measures will be implemented
What you need to know
  • Working hours are Monday-Friday (7:00 am to 9:00 pm). Work on the weekends and at night will require City approval
  • The contractor will notify property owners if work will impact access to property
  • Please do not remove any construction stakes located within the limits of work


N James Street project update - 4/25/2017:

Weather permitting, the North James Street & Bridge Improvements project will begin May 1, 2017. The Contractor, Alliance Construction Group, will begin with "Phase 3", which is from NE 14th CT to Beaverbrooke Blvd. Beaverbrooke Blvd intersection will be open during this Phase 3 work. The phasing needed to be revised due to private utility relocations and lead time for the precast culvert. This revision in phasing gives the Contractor the best opportunity to complete this project in the 2017 construction season. Note that the N. James Street trail will be closed in this Phase 3 area. See image for proposed detour. We have yet to receive a detailed construction schedule from the contractor. That information will be posted as it becomes available.
Proposed Detour

A Public Information Meeting was held on December 19th 2016 at the Grimes Community Complex.
Meeting Details  (PDF)
Map of Project Area  (PDF)
Video of Meeting